What We Do
Demonstrator, pilot, prototype
With our partners we develop pilot prototypes and plan designs.
Documents/Report
More than 30 reports are being implemented by our partners
Software
Our partners develop ICT software, complete with validation and test cert
Toolkit
Our partners develop training report: interdisciplinary training and transferable skills
DELIVERABLES
REPORT
Quality assurance Plan (QAP)
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
REPORT
Risk management Plan
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
ORDP: Open Research Data Pilot
Data management plan
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
REPORT
Gender & Diversity Adoption and use of SAT
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
REPORT
Common Project Framework, detailed research plans for each WP
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
REPORT
Dissemination and CommunicationPlan, materials and channels
Estimated delivery date: 30 Jun 2020
Lead Partner: UCC
Demonstrator
First Trial report and optimisation recommendations for trial 2
Estimated delivery date: 30 Jun 2023
Lead Partner: PLOCAN
Demonstrator
Trial 2 completion validation report at TRL7
Estimated delivery date: 30 Sep 2020
Lead Partner: INSB
REPORT
Data report for dissemination plan
Estimated delivery date: 30 Sep 2024
Lead Partner: PLOCAN
REPORT
Resource, demand, future resource & demand and site survey
Estimated delivery date: 31 Dec 2020
Lead Partner: UCC
REPORT
Life Cycle analysis report
Estimated delivery date: 31 Dec 2020
Lead Partner: UCC
REPORT
Health and Safety Strategy and Plan
Estimated delivery date: 31 Dec 2020
Lead Partner: HWU
DEMONSTRATOR
Designs for port facilities construction, logistics, and support vessels
Estimated delivery date: 31 Dec 2020
Lead Partner: UoAeg
REPORT
Compliance and standardization report
Estimated delivery date: 31 Dec 2020
Lead Partner: INSB
REPORT
Initial report on Innousses PE, QH and RRI to incorporate into designs
Estimated delivery date: 31 Dec 2020
Lead Partner: HWU
REPORT
Knowledge and IP plan
Estimated delivery date: 31 Dec 2020
Lead Partner: UCC
REPORT
Environmental Impact, environmental and consenting requirements
Estimated delivery date: 31 Dec 2021
Lead Partner: INSB
REPORT
Report with sign-offs, Grid consent licence, confirming the Innousses island grid is ready for go-live with the MUSICA connection to MUP
Estimated delivery date: 31 Dec 2021
Lead Partner: NeoDyne
Report
Sign-off certification report for completed MUP constructions at Coral shipyards: MUP, RES, Desalination, EMS, Storage
Estimated delivery date: 31 Dec 2021
Lead Partner: INSB
REPORT
Market research on EU islands and SIDS of the MUSICA solution
Estimated delivery date: 31 Dec 2021
Lead Partner: UCC
REPORT
Policy brief on Public engagement, SDG alignment impacts and final RRI methodology report
Estimated delivery date: 31 Dec 2023
Lead Partner: HWU
REPORT
Final Impact Assessment report of MUSICA
Estimated delivery date: 31 Dec 2024
Lead Partner: UCC
REPORT
Policy brief on H&S, Regulations, non-technical barriers & mitigation
Estimated delivery date: 31 Dec 2024
Lead Partner: HWU
REPORT
Policy brief on R&I & technology on MUP/MUS & small island issues
Estimated delivery date: 31 Dec 2024
Lead Partner: PLOCAN
REPORT
Final report on Innousses public and QH engagement and RRI
Estimated delivery date: 31 Dec 2024
Lead Partner: ICoRSA
OTHER
Training report: interdisciplinary training and transferable skills
Estimated delivery date: 31 Dec 2024
Lead Partner: HWU
REPORT
Report on investor relations
Estimated delivery date: 31 Dec 2024
Lead Partner: UCC
REPORT
Consolidate policy briefs on technical and non-technical barriers
Estimated delivery date: 31 Dec 2024
Lead Partner: UCC
REPORT
End of project Dissemination and Communication report
Estimated delivery date: 31 Jan 2020
Lead Partner: UCC
REPORT
Report on best practice for containerisation of a product
Estimated delivery date: 31 Mar 2020
Lead Partner: UCC
REPORT
Grid studies report, and documentation for Grid Consent Licence
Estimated delivery date: 31 Mar 2021
Lead Partner: NeoDyne
REPORT
Sign-off certification report for other installed infrastructure in sea around MUP: cable to shore, aquaculture cage, buoy, island infrastruct
Estimated delivery date: 31 Mar 2022
Lead Partner: INSB
REPORT
Plans and test protocols for the sea trial, instrumentation, SCADA
Estimated delivery date: 31 Mar 2022
Lead Partner: PLOCAN
REPORT
Policy brief on ICT and electrical for Marine RES for small islands
Estimated delivery date: 31 Mar 2024
Lead Partner: NeoDyne